HSBC Holdings reportedly sold about $300 million of a construction loan tied to a giant New Mexico AI data center at a discount, a sale that suggests lenders are getting more cautious about AI data center debt

2

1

.

Source: Quartz

Source: Quartz

A slice of an $18 billion loan

The loan funds Project Jupiter, a planned 2.45-gigawatt campus in southern New Mexico

2

1

3

. The campus is part of the Stargate AI build-out announced by President Trump in early 2025 alongside Oracle, OpenAI and SoftBank leaders

2

1

3

.

Per Bloomberg, buyers paid in the mid-80s cents on the dollar, meaning a little over 80 cents for each dollar of loan value, and the exact price was not disclosed

2

1

3

. The deal happened several weeks before the reports surfaced

2

1

.

It is a slice of Project Miner, an $18 billion financing package put together by about 20 banks in late 2025 for the campus

2

1

. The slice the bank sold is a small fraction of the roughly $18 billion package, per Bloomberg

2

1

. Neither company has confirmed the sale: the bank declined to comment and Oracle had no immediate comment

1

3

.

Why a bank sells at a loss

Because construction lenders typically hold the debt on their own books, getting out before completion can mean accepting a discount bigger than the upfront fees earned, per Bloomberg

2

1

.

The sale came weeks after Oracle sent a force majeure notice in September to the developer, a Blue Owl Capital unit

2

1

3

. The notice, a contract mechanism for events outside a party's control, would allow payment deferral if the project is derailed

2

1

3

. Per people familiar with the matter, it was aimed at deferring payments should regulatory hurdles jeopardize the project, though Oracle publicly said the project remains on schedule

2

1

3

.

The project has faced local opposition and slow air and pipeline permits

2

1

3

. A gas pipeline was also sent on a new route after state regulators balked at the original path, pushing the target in-service date to next year

2

1

3

. Blue Owl said the notice does not change its financial commitments to the project

1

.

Regulators and markets add pressure

Per Bloomberg, the sale fits a broader reassessment of AI-related debt exposure amid regulatory pushback after the Democratic electoral sweep and uncertainty following Jensen Huang's departure as Nvidia CEO

2

1

. On November 5, the Nasdaq fell 4.5% in a post-midterm selloff that erased about $3 trillion in market value from companies in the Standard & Poor's 500 index

3

.

Texas Governor-elect Gina Hinojosa has announced the state will regulate data center construction, citing environmental impact and public access to federal lands

3

. Texas hosts nearly a quarter of US data centers, so the pushback now reaches beyond New Mexico

3

.