HSBC sold a slice of an Oracle-linked data center loan at a discount
The bank sold about $300 million of an $18 billion loan for Oracle's New Mexico campus at prices in the mid-80s HSBC Holdings sold about $300 million of an $18 billion construction loan for an Oracle $ORCL-linked data center in New Mexico at a discount, according to Bloomberg. The sale followed a
[2]
HSBC offloads $300 million troubled AI data center loan at steep discount - report By Investing.com
Investing.com -- HSBC Holdings PLC (NYSE:HSBC) offloaded a roughly $300 million portion of a construction loan tied to a troubled New Mexico data center project at a steep discount, according to Bloomberg. The sale, executed at prices in the mid-80s several weeks ago, underscores mounting lender
[3]
HSBC Sold a $300m Loan for the Construction of a New Mexico Data Center
HSBC Holdings offloaded a $300m stake in an $18bn data center construction loan, rattling investors amid a wave of regulatory pressure on large-scale AI infrastructure projects. HSBC Holdings reportedly sold at a steep discount an approximately $300m portion of an $18bn construction financing
Share
Copy Link
HSBC Holdings reportedly sold about $300 million of a construction loan tied to a giant New Mexico AI data center at a discount, a sale that suggests lenders are getting more cautious about AI data center debt
2
1
.
Source: Quartz
The loan funds Project Jupiter, a planned 2.45-gigawatt campus in southern New Mexico
2
1
3
. The campus is part of the Stargate AI build-out announced by President Trump in early 2025 alongside Oracle, OpenAI and SoftBank leaders2
1
3
.Per Bloomberg, buyers paid in the mid-80s cents on the dollar, meaning a little over 80 cents for each dollar of loan value, and the exact price was not disclosed
2
1
3
. The deal happened several weeks before the reports surfaced2
1
.It is a slice of Project Miner, an $18 billion financing package put together by about 20 banks in late 2025 for the campus
2
1
. The slice the bank sold is a small fraction of the roughly $18 billion package, per Bloomberg2
1
. Neither company has confirmed the sale: the bank declined to comment and Oracle had no immediate comment1
3
.Because construction lenders typically hold the debt on their own books, getting out before completion can mean accepting a discount bigger than the upfront fees earned, per Bloomberg
2
1
.The sale came weeks after Oracle sent a force majeure notice in September to the developer, a Blue Owl Capital unit
2
1
3
. The notice, a contract mechanism for events outside a party's control, would allow payment deferral if the project is derailed2
1
3
. Per people familiar with the matter, it was aimed at deferring payments should regulatory hurdles jeopardize the project, though Oracle publicly said the project remains on schedule2
1
3
.The project has faced local opposition and slow air and pipeline permits
2
1
3
. A gas pipeline was also sent on a new route after state regulators balked at the original path, pushing the target in-service date to next year2
1
3
. Blue Owl said the notice does not change its financial commitments to the project1
.Related Stories
Per Bloomberg, the sale fits a broader reassessment of AI-related debt exposure amid regulatory pushback after the Democratic electoral sweep and uncertainty following Jensen Huang's departure as Nvidia CEO
2
1
. On November 5, the Nasdaq fell 4.5% in a post-midterm selloff that erased about $3 trillion in market value from companies in the Standard & Poor's 500 index3
.Texas Governor-elect Gina Hinojosa has announced the state will regulate data center construction, citing environmental impact and public access to federal lands
3
. Texas hosts nearly a quarter of US data centers, so the pushback now reaches beyond New Mexico3