Meta breaks ground on over $1 billion data center in Oklahoma's Tulsa
April 21 (Reuters) - Meta Platforms (META.O), opens new tab said on Tuesday it has begun construction on a new data center in Tulsa, Oklahoma, a project valued at more than $1 billion, as the Facebook-parent races to build AI infrastructure for securing computing power. Like its Big Tech peers, Meta is locked in an intensifying race to build out massive data centers to power its ambitious superintelligence bet, even as environmental and consumer groups increasingly push back against the energy-intensive expansion. Here are the details: Reporting by Jaspreet Singh in Bengaluru; Editing by Devika Syamnath Our Standards: The Thomson Reuters Trust Principles., opens new tab
[2]
Meta breaks ground on over $1 billion data center in Oklahoma's Tulsa
Meta Platforms is constructing a massive $1 billion data centre in Tulsa, Oklahoma, to boost its AI infrastructure. This investment will create over 1,000 construction jobs and 100 operational roles, marking Meta's first facility in the state. The project underscores the company's aggressive push into artificial intelligence. Meta Platforms said on Tuesday it has begun construction on a new data centre in Tulsa, Oklahoma, a project valued at more than $1 billion, as the Facebook-parent races to build AI infrastructure for securing computing power. Like its Big Tech peers, Meta is locked in an intensifying race to build out massive data centres to power its ambitious superintelligence bet, even as environmental and consumer groups increasingly push back against the energy-intensive expansion. The company said the Tulsa data centre is expected to create more than 1,000 construction jobs at its peak and about 100 operational jobs upon completion. This will be Meta's first data centre in Oklahoma and it will be located at the Fair Oaks Innovation Park, spanning more than 2 million square feet, according to the company. Meta said it will pay the full cost of water and wastewater service required to support the data centre site. "We produce more energy than we consume in Oklahoma, giving companies like Meta the reliable and affordable power they need to grow and innovate," said Governor Kevin Stitt. Fortis Construction is the general contractor for the project. Meta said the Tulsa data centre marks its 28th U.S. facility and 32nd worldwide. Last week, Reuters reported that Meta intends to conduct a first wave of sweeping layoffs planned for this year on May 20, with more coming later. CEO Mark Zuckerberg is pumping hundreds of billions of dollars into AI as he seeks to dramatically reshape his company's inner workings around the technology.
[3]
Meta breaks ground on over $1 billion data center in Oklahoma's Tulsa
April 21 (Reuters) - Meta Platforms said on Tuesday it has begun construction on a new data center in Tulsa, Oklahoma, a project valued at more than $1 billion, as the Facebook-parent races to build AI infrastructure for securing computing power. Like its Big Tech peers, Meta is locked in an intensifying race to build out massive data centers to power its ambitious superintelligence bet, even as environmental and consumer groups increasingly push back against the energy-intensive expansion. Here are the details: o The company said the Tulsa data center is expected to create more than 1,000 construction jobs at its peak and about 100 operational jobs upon completion. o This will be Meta's first data center in Oklahoma and it will be located at the Fair Oaks Innovation Park, spanning more than 2 million square feet, according to the company. o Meta said it will pay the full cost of water and wastewater service required to support the data center site. o "We produce more energy than we consume in Oklahoma, giving companies like Meta the reliable and affordable power they need to grow and innovate," said Governor Kevin Stitt. o Fortis Construction is the general contractor for the project. o Meta said the Tulsa data center marks its 28th U.S. facility and 32nd worldwide. o Last week, Reuters reported that Meta intends to conduct a first wave of sweeping layoffs planned for this year on May 20, with more coming later. o CEO Mark Zuckerberg is pumping hundreds of billions of dollars into AI as he seeks to dramatically reshape his company's inner workings around the technology. (Reporting by Jaspreet Singh in Bengaluru; Editing by Devika Syamnath)
Share
Share
Copy Link
Meta Platforms has started construction on a new data center in Tulsa, Oklahoma, valued at over $1 billion as part of its aggressive AI infrastructure expansion. The project will create more than 1,000 construction jobs and 100 operational roles, marking Meta's first facility in the state and its 28th U.S. data center overall.
Meta Platforms has broken ground on a new data center in Tulsa, Oklahoma, marking a significant expansion of the company's AI infrastructure capabilities
1
. The $1 billion investment represents the Facebook parent company's first facility in Oklahoma and underscores the intensifying competition among Big Tech companies to secure computing power for artificial intelligence development2
. Located at Fair Oaks Innovation Park, the facility will span more than 2 million square feet, positioning it as a critical component in Meta's superintelligence bet.
Source: ET
The Tulsa project is expected to generate substantial employment opportunities, creating more than 1,000 construction jobs at its peak and approximately 100 operational roles upon completion
3
. Fortis Construction has been selected as the general contractor for the project. Oklahoma Governor Kevin Stitt emphasized the state's competitive advantage, noting that "We produce more energy than we consume in Oklahoma, giving companies like Meta the reliable and affordable power they need to grow and innovate"2
. This energy surplus positions Oklahoma as an attractive destination for energy-intensive data center operations, a factor that becomes increasingly important as Meta and other Big Tech expansion accelerates.The new data center in Tulsa marks Meta's 28th U.S. facility and 32nd worldwide, reflecting CEO Mark Zuckerberg's commitment to pumping hundreds of billions of dollars into AI as he seeks to dramatically reshape the company's operations around the technology
3
. Meta has committed to paying the full cost of water and wastewater services required to support the data center site, addressing infrastructure concerns upfront2
. This investment comes even as environmental and consumer groups increasingly push back against the energy-intensive expansion of data centers across the country .
Source: Reuters
Related Stories
The announcement arrives as Meta navigates significant organizational changes. According to Reuters, the company intends to conduct a first wave of sweeping layoffs on May 20, with additional cuts planned later in the year
3
. This juxtaposition highlights Meta's strategic priority: redirecting resources toward AI infrastructure while streamlining other operations. The contrast between workforce reductions and massive capital investments signals that Meta views data center capacity as essential to competing in the AI race, where access to computing power increasingly determines competitive advantage. As Big Tech peers pursue similar strategies, the battle to secure computing power through expanded data center networks will likely intensify, making projects like the Tulsa facility critical to maintaining technological leadership in artificial intelligence development.Summarized by
Navi
[3]
15 Oct 2025•Technology

26 Mar 2026•Business and Economy

11 Feb 2026•Technology

1
Policy and Regulation

2
Technology

3
Business and Economy