NTT Data reportedly nears deal to build Anthropic's first Japan data centre
The Osaka facility could cost up to ¥1tn ($6.3bn) to build and draw up to 500 megawatts, Nikkei Asia reports. TT Data Group is close to agreeing to a deal with Anthropic for a new data centre in Osaka, Nikkei Asia reported on Tuesday, citing multiple sources. It would be the first site in Japan
[2]
NTT Data in final talks to build Anthropic's first data centre in Japan, Nikkei reports
TOKYO, Oct 13 (Reuters) - Japan's NTT Data Group, a unit of telecommunications giant NTT, is in the final stages of talks to build a data centre in Osaka, western Japan, for US AI company Anthropic, the Nikkei business daily reported on Tuesday, citing multiple sources. o Construction costs could
Share
Copy Link
NTT Data Group is in final talks with Anthropic to construct a massive data centre in Osaka, marking the US AI company's first dedicated facility in Japan. The project could cost up to 1 trillion yen ($6.3 billion) for construction alone and draw 500 megawatts of power, making it one of Japan's largest data centres with partial operations targeted for 2028.
NTT Data Group is approaching a final agreement with Anthropic to build a data centre in Osaka, marking a significant expansion for the US AI company in Asian markets. According to Nikkei, citing multiple sources, this would be Anthropic's first data centre in Japan dedicated exclusively to supporting its Claude AI models
1
2
. The two companies aim to finalize the deal by March 31, 2027, the end of Japan's fiscal year 2026, with partial operations potentially starting as early as 20282
. Both NTT Data and Anthropic declined to comment on the report1
.Source: Market Screener
Construction costs for the data center in Osaka could reach up to 1 trillion yen ($6.3 billion), representing one of the largest AI infrastructure development projects in Japan
1
2
. This figure covers construction alone, with the total investment climbing to several trillion yen once AI servers equipped with graphics processors are added to handle demanding AI workloads1
. The facility would draw up to 500 megawatts of power, positioning it among Japan's largest data centres by capacity1
2
. NTT Data, a unit of telecommunications giant NTT, ranks third globally among data centre operators and currently manages over 1,600 megawatts of capacity across multiple countries1
.Securing adequate power supply presents the primary obstacle for this ambitious project. Drawing 500 megawatts directly from Japan's electrical grid would take considerable time, prompting the partners to explore alternative solutions
1
. The project will initially investigate on-site electricity generation and fuel cells as faster paths to meeting the facility's substantial energy requirements1
. This approach reflects broader industry challenges as AI companies race to build infrastructure capable of supporting increasingly power-hungry models while navigating local grid constraints.Related Stories
Anthropichas already established a presence in Japan through its partnership with Hitachi, which agreed in May to deploy Claude AI models across its workforce of approximately 290,000 employees
1
. The company is simultaneously exploring data centre opportunities in other Asian countries, where governments are actively competing to attract such facilities1
. In Australia, the Australian Financial Review reported that Anthropic is holding discussions with local firms about potential projects1
. This multi-country strategy positions the US AI company to serve regional demand while diversifying its infrastructure footprint.
Source: The Next Web
Japan is aggressively pursuing data centre investments as part of a national strategy to strengthen its position in cloud computing and AI. The government has set an ambitious target of attracting 32.7 trillion yen in combined public and private investment for data centres, cloud computing infrastructure, and battery storage by 2035
1
. Beyond the Osaka project, additional large-scale facilities are planned for Akita and Kagoshima, according to Nikkei1
. This coordinated push reflects Japan's recognition that hosting major AI infrastructure will be critical for economic competitiveness as artificial intelligence reshapes global industries. Watch for how Japan's regulatory framework and energy policies evolve to accommodate these power-intensive facilities, and whether other AI companies follow Anthropic's lead in establishing dedicated Japanese operations.Summarized by