Japan Launches $140B AI Infrastructure Push with Dell, JERA to Close Gap with US and China

6 Sources

Share

JERA, Dell Technologies and RHAELM unveiled a $140 billion plan to build 3-4 gigawatts of AI data centers across Japan within five years. The partnership aims to position Japan as the world's largest AI infrastructure hub outside the US and China, starting with a $15 billion, 400-megawatt hyperscale data center near Tokyo backed by Apollo Global Management.

Japan Targets Massive AI Infrastructure Expansion

Japan AI infrastructure is set for a dramatic transformation as JERA, the world's largest gas trader, Dell Technologies, and UK-based AI infrastructure developer RHAELM announced a $140 billion initiative to develop 3 to 4 gigawatts of AI data center capacity within five years

2

. The ambitious plan addresses Japan's significant AI infrastructure gap, with the country currently consuming just 1.7 gigawatts of electricity for data centers compared to 29.2 gigawatts in the US and 8.5 gigawatts in China

2

. The three companies signed a memorandum of understanding on Thursday to develop a standardized framework for building AI infrastructure at a national scale, with Apollo Global Management serving as the strategic investment and financial partner for RHAELM

1

.

$15 Billion Chiba Hyperscale Data Center Leads the Charge

The AI infrastructure development in Japan begins with a $15 billion, 400-megawatt hyperscale data center in Chiba, adjacent to JERA's existing thermal power station near Tokyo

1

. This facility will become Asia's largest AI data center project outside China when operations begin in phases around 2028, reaching full 400 MW capacity in 2029

1

. The project's innovative approach bypasses traditional electricity supply constraints by drawing power directly from the Chiba Thermal Power Station rather than connecting to the national grid

2

. JERA will supply 400 MW of power capacity under a 15- to 25-year agreement, while Dell will provide standardized, rack-scale AI infrastructure

1

. "The keyword is speed to power," said Yukio Kani, global chief executive of JERA, citing the company's portfolio of 35 million tonnes of liquefied natural gas traded annually that can fire power stations

2

.

Source: TechRadar

Source: TechRadar

Standardized Framework Accelerates Development Timeline

The partnership aims to create a standardized, repeatable and scalable model from the outset, reducing the lengthy lead times and complexity involved in developing each project independently

1

. "We can deliver a 400MW facility years ahead of a conventional grid-connected timeline," said Bradd Lewis, RHAELM's chief executive

3

. This standardized framework for AI computing power development assigns clear roles: JERA brings land and power through its gas-fired power generation capabilities, Dell Technologies supplies ready-built racks of servers, and RHAELM manages construction and operations

3

. The companies estimate each gigawatt costs $35 billion to $45 billion, implying the overall $140 billion investment for the planned capacity

2

. The partners intend to replicate this model at other JERA power stations, with potential global expansion beyond Japan

1

.

Dell's AI-Server Business Drives Partnership

Dell Technologies brings substantial momentum to the AI data centre push, with the company reporting record AI-server orders of $60.9 billion in its latest quarter and AI-server revenue hitting $16.4 billion

5

. The company ended the period with a $95 billion AI-server backlog and now expects $74 billion in fiscal 2027 AI-server revenue

5

. Dell shares rose approximately 1% to $545 in premarket trading following the announcement

5

. The $15 billion figure for the Chiba project covers land, power infrastructure, construction and computing equipment rather than representing a Dell contract of that size alone

5

.

Japan Races to Avoid Becoming an "AI Colony"

The initiative addresses growing concerns about Japan's position in the global AI race. Japan's digital minister has warned the country could become an "AI colony" if it falls behind in developing domestic AI computing power

3

. The Japanese government is targeting ¥32.7 trillion ($206 billion) of public-private investment in cloud computing and data center infrastructure by 2035 as part of Prime Minister Sanae Takaichi's plan to invest in strategically important sectors

2

. "If you see Asia outside China, Japan is a major data centre market," Kani told the Financial Times

2

. The country already hosts major operators including NTT Data and SoftBank, while private equity firm Blackstone announced a separate $30 billion expansion programme for Japan AI data centers over the coming years

2

. The JERA-Dell-RHAELM partnership represents a significant step toward positioning Japan as a major hub for AI infrastructure outside the US and China, with the potential for global expansion of their standardized model

4

.

Source: The Next Web

Source: The Next Web