JERA teams up with Dell, RHAELM on AI infrastructure development in Japan
TOKYO, Oct 1 (Reuters) - Japan's biggest power generator JERA will partner with Dell Technologies (DELL.N), opens new tab and UK-based AI infrastructure developer RHAELM to accelerate the development of AI infrastructure in Japan, the three companies said on Thursday. They signed a memorandum of
[2]
Japan plans $140bn AI data centre push with Dell and Jera
Japan is aiming to speed up data centre development with a $140bn investment scheme leveraging its powerful gas trading company in a bid to become the world's largest AI infrastructure hub outside the US and China. A trio of companies, including Dell and Jera, the world's largest gas trader,
[3]
Japan eyes $140bn AI data centre push with Dell and JERA
JERA, Dell and UK developer RHAELM signed a non-binding agreement on Thursday, JERA said. Private equity firm Apollo will help fund the work as RHAELM's financing partner. The first project sits next to JERA's gas-fired power station in Chiba, east of Tokyo. It will draw about 400 megawatts and
[4]
Japan wants to close its AI infrastructure gap with Dell, Apollo and Jera
Japan's data centers consume just 1.7GW, but this could change soon * Dell, Apollo and Jera plan up to 4GW of AI infrastructure within five years * A $15bn Tokyo project will launch Japan's biggest AI infrastructure push yet * Jera wants gas power and AI computing facilities developed at
[5]
Dell Joins $15B Japan AI Data Center Project - Dell Technologies (NYSE:DELL)
Dell Technologies Inc. (NYSE:DELL) is joining a more than $15 billion AI data center plan in Japan designed to sidestep one of the biggest constraints on the AI buildout: getting enough electricity to computing infrastructure quickly. Japan's JERA, Dell and UK developer RHAELM said Thursday they
[6]
Jera, Dell Team Up for $15 Billion AI Infrastructure Project in Japan
Japan's Jera, Dell Technologies and U.K.-based infrastructure firm Rhaelm are teaming up on an artificial-intelligence infrastructure project that could cost more than $15 billion to develop. The three companies signed an agreement to develop a standardized framework to accelerate AI
Share
Copy Link
JERA, Dell Technologies and RHAELM unveiled a $140 billion plan to build 3-4 gigawatts of AI data centers across Japan within five years. The partnership aims to position Japan as the world's largest AI infrastructure hub outside the US and China, starting with a $15 billion, 400-megawatt hyperscale data center near Tokyo backed by Apollo Global Management.
Japan AI infrastructure is set for a dramatic transformation as JERA, the world's largest gas trader, Dell Technologies, and UK-based AI infrastructure developer RHAELM announced a $140 billion initiative to develop 3 to 4 gigawatts of AI data center capacity within five years
2
. The ambitious plan addresses Japan's significant AI infrastructure gap, with the country currently consuming just 1.7 gigawatts of electricity for data centers compared to 29.2 gigawatts in the US and 8.5 gigawatts in China2
. The three companies signed a memorandum of understanding on Thursday to develop a standardized framework for building AI infrastructure at a national scale, with Apollo Global Management serving as the strategic investment and financial partner for RHAELM1
.The AI infrastructure development in Japan begins with a $15 billion, 400-megawatt hyperscale data center in Chiba, adjacent to JERA's existing thermal power station near Tokyo
1
. This facility will become Asia's largest AI data center project outside China when operations begin in phases around 2028, reaching full 400 MW capacity in 20291
. The project's innovative approach bypasses traditional electricity supply constraints by drawing power directly from the Chiba Thermal Power Station rather than connecting to the national grid2
. JERA will supply 400 MW of power capacity under a 15- to 25-year agreement, while Dell will provide standardized, rack-scale AI infrastructure1
. "The keyword is speed to power," said Yukio Kani, global chief executive of JERA, citing the company's portfolio of 35 million tonnes of liquefied natural gas traded annually that can fire power stations2
.
Source: TechRadar
The partnership aims to create a standardized, repeatable and scalable model from the outset, reducing the lengthy lead times and complexity involved in developing each project independently
1
. "We can deliver a 400MW facility years ahead of a conventional grid-connected timeline," said Bradd Lewis, RHAELM's chief executive3
. This standardized framework for AI computing power development assigns clear roles: JERA brings land and power through its gas-fired power generation capabilities, Dell Technologies supplies ready-built racks of servers, and RHAELM manages construction and operations3
. The companies estimate each gigawatt costs $35 billion to $45 billion, implying the overall $140 billion investment for the planned capacity2
. The partners intend to replicate this model at other JERA power stations, with potential global expansion beyond Japan1
.Related Stories
Dell Technologies brings substantial momentum to the AI data centre push, with the company reporting record AI-server orders of $60.9 billion in its latest quarter and AI-server revenue hitting $16.4 billion
5
. The company ended the period with a $95 billion AI-server backlog and now expects $74 billion in fiscal 2027 AI-server revenue5
. Dell shares rose approximately 1% to $545 in premarket trading following the announcement5
. The $15 billion figure for the Chiba project covers land, power infrastructure, construction and computing equipment rather than representing a Dell contract of that size alone5
.The initiative addresses growing concerns about Japan's position in the global AI race. Japan's digital minister has warned the country could become an "AI colony" if it falls behind in developing domestic AI computing power
3
. The Japanese government is targeting ¥32.7 trillion ($206 billion) of public-private investment in cloud computing and data center infrastructure by 2035 as part of Prime Minister Sanae Takaichi's plan to invest in strategically important sectors2
. "If you see Asia outside China, Japan is a major data centre market," Kani told the Financial Times2
. The country already hosts major operators including NTT Data and SoftBank, while private equity firm Blackstone announced a separate $30 billion expansion programme for Japan AI data centers over the coming years2
. The JERA-Dell-RHAELM partnership represents a significant step toward positioning Japan as a major hub for AI infrastructure outside the US and China, with the potential for global expansion of their standardized model4
.