Oracle moves gas by trucks to keep its AI data centres on schedule
Deliveries by road kept a site outside Salt Lake City running for more than a year while a pipeline was built, are powering early work at an OpenAI campus in Texas, and are now under consideration at Project Jupiter in New Mexico, where the state land office twice refused rights-of-way for the
[2]
Oracle trucks natural gas to AI data centers amid pipeline delays
The company used the approach at a Utah facility for over a year and is now weighing it for a stalled New Mexico project with a 2.45-gigawatt target Oracle $ORCL is delivering compressed natural gas by truck to several of its AI data centers as pipeline construction delays threaten to slow the
[3]
Oracle's 'force majeure' warning lands as AI power gets scarce
For more than a year, an Oracle Corp. (ORCL) data center outside Salt Lake City ran on natural gas that arrived by truck, according to Bloomberg. Oracle now wants to repeat that move at Project Jupiter, an AI campus in New Mexico built for OpenAI. The difference is size, and that is where a clever
Share
Copy Link
Oracle is trucking compressed natural gas to AI data centers at four times the cost of pipeline delivery as construction delays threaten its buildout. The strategy powered a Utah site for over a year and now supports OpenAI's Texas campus, but scaling it to Project Jupiter's 2.45-gigawatt capacity in New Mexico would require nearly 900 deliveries daily.

Oracle is trucking compressed natural gas to AI data centers that cannot yet connect to pipelines, paying roughly four times the price of gas at a major hub to keep construction on schedule
1
. The approach sustained operations at a site outside Salt Lake City for more than a year while a pipeline was built, is currently powering early work at an OpenAI campus in Shackelford County, Texas, and is now under consideration at Project Jupiter in New Mexico2
. Oracle shares fell approximately 5.5% following reports of the company's reliance on this costly workaround3
.The industry calls this a virtual pipeline. Compressed natural gas is drawn from a real pipeline, compressed into trailers, driven for hours, then decompressed to power generators
1
. According to East Daley Analytics, delivered gas runs about four times the price of gas at a major hub once labor, equipment, and the trucks' own fuel are counted2
. At the Utah facility, Oracle's gas deliveries were handled by Certarus, a unit of Superior Plus Corp, while in Texas, they are provided by VoltaGrid LLC2
.Pipeline construction delays are forcing Oracle to consider trucked natural gas for Project Jupiter, where the New Mexico State Land Office twice refused rights-of-way for Energy Transfer's pipeline
1
. Land Commissioner Stephanie Garcia Richard denied the right-of-way in March and July, citing emissions and water strain3
. The pipeline has been rerouted across federal land, and its start date slipped to February 1, 20273
.Oracle sent a force majeure notice to Jupiter's developer, a unit of Blue Owl Capital, last month
3
. The notice formally claims that events beyond Oracle's control could stall the 2.45-gigawatt campus3
. If both sides agree a power-related force majeure event occurred, Oracle could delay rent for three years once payments start, though it would still owe full rent over the lease3
. About 20 banks provided an $18 billion construction loan that now trades below 90 cents on the dollar3
.Powering AI data centers through trucked natural gas faces severe physical limitations. Powering just 100 megawatts of capacity would require each large trailer to supply roughly 40 minutes of electricity, according to Ellie Holbrook, an energy analyst at SemiAnalysis
2
. Scaled to Project Jupiter's full 2.45-gigawatt capacity, that pace implies close to 900 deliveries daily3
. No trucking network is built for that volume3
.The segment New Mexico refused covered just 0.63 miles of state trust land, yet that strip helped delay fuel for a project valued at up to $165 billion by nearly six months
3
. Trucks can energize the first building, but the campus still needs its pipeline to reach full capacity3
. The AI buildout was first limited by chips, then by grid connections, and now runs through permit offices3
.Related Stories
Oracle's AI infrastructure expansion has strained the company's finances significantly. Capital expenditures reached $28.5 billion in the quarter ended August 31, up from $8.5 billion in the same period a year earlier
2
. The company reported negative free cash flow of $5.4 billion for that quarter and has said it plans to raise approximately $40 billion through a combination of debt and equity in its current fiscal year2
.Oracle's contracted backlog reached $664 billion in the quarter ended August 31, 2026, but that backlog becomes revenue only when AI data centers switch on
3
. Every month of delay widens the gap between spending and payback3
. Oracle shares are down about 52% over the past year and trade near 16 times forward earnings, despite cloud infrastructure sales jumping 121% last quarter3
.The bottleneck affecting powering AI data centers is the same on both sides of the Atlantic
1
. Nscale's £2 billion Essex site, with Microsoft as anchor tenant, cannot get 90 megawatts in time for a planned 2027 opening, and some British grid waits run close to a decade1
. Denmark stopped taking applications altogether, with its grid operator Energinet halting all new connection agreements this year, facing a queue of roughly 60 gigawatts against national peak demand of 7 gigawatts1
.A draft Spanish decree would require new data centres above 1 megawatt to meet 80% of demand hourly from renewables or lose their grid connection, giving projects already in permitting six months to comply without compensation
1
. AI cloud demand is outrunning supply, creating pressure to find alternative energy infrastructure solutions3
. An empty data hall earns nothing, so expensive gas still beats waiting, even as Oracle's free cash flow remains negative3
.Summarized by
Navi
[3]
19 Sept 2026•Business and Economy

21 Aug 2025•Business and Economy

12 Dec 2025•Business and Economy

1
Technology

2
Technology

3
Business and Economy