Uniper nears first deal to repurpose disused power plants for data centres
German utility seeks 'double benefit' from monetising dormant but grid-linked sites and boosting demand for its energy State-owned utility Uniper is closing in on its first deal to convert disused power plants into data centre sites, as it embarks on an effort to tap AI demand ahead of a sale or
[2]
Uniper nears first data centre deal on idle power plant site - report By Investing.com
Investing.com -- Germany's state-owned Uniper is close to its first deal to sell or lease a disused power plant site to a data centre developer, the Financial Times reported on Monday, as it seeks to highlight potential growth from artificial intelligence ahead of a planned government sale or
Share
Copy Link
Uniper is close to its first deal to turn a disused power plant site into a data centre. The state-owned utility has 700MW of grid capacity lined up as Berlin prepares to sell.
Uniper is nearing a first deal to sell or lease one of its disused power plant sites for a data centre, according to people familiar with the negotiations
1
,2
. If completed, it would be the state-owned German utility's first move into the land rush around AI computing, and a way to earn from assets it no longer needs.
Source: FT
The near-deal sits on a bigger base. Uniper has flagged 10 unused sites it thinks could attract hyperscalers or other investors, in the UK, Germany, Sweden and the Netherlands
1
,2
. It is in advanced talks on two more1
,2
. Chief executive Michael Lewis says about 700MW of grid capacity is already secured across its disused sites1
,2
. That is enough for roughly seven hyperscale data centres, or 70 smaller ones, on International Energy Agency demand estimates1
.Lewis calls the setup a "double benefit": rising power demand helps the existing generation business, and the land itself can be repurposed for data centres
1
. The pull for buyers is the grid. Uniper's former plant sites come with connections already in place, sparing developers cost and queues that, per the International Energy Agency, run two to 10 years across EU countries1
,2
.Uniper has not disclosed what any site might fetch
1
,2
. Bank analysts put similar deals at about €1mn per megawatt, which would make the 700MW worth roughly €700mn1
,2
.Uniper has company in this market. One German rival is developing 10 sites with 3GW of grid capacity and last year sold Amazon a former British coal plant for €203mn
1
,2
. Drax plans a data centre at its wood-fired Yorkshire power station1
.Timing is the political part. Uniper was once Europe's biggest importer of Russian gas. Berlin rescued it in 2022 after Moscow cut supplies in the sanctions fallout over Ukraine
1
,2
. The government must sell or list the company to satisfy EU conditions attached to approving that rescue1
,2
. A fresh growth story makes the asset easier to sell.The data-centre plan sits inside a bigger one. Uniper intends to invest €6bn by the early 2030s in flexible generation, including building or modifying gas plants, alongside data-centre infrastructure and renewables
1
,2
.Per the FT's reporting, Uniper's push comes amid growing market jitters about whether the AI investment boom can last
1
. "We are not making a speculative bet on AI valuations. We are positioning physical infrastructure we already own for one of the most significant sources of structural power-demand growth in Europe," Lewis said1
. "Europe is not going to lose the AI race in the lab. It will lose it at the substation," he said1
. Centrica, Equinor and a consortium of Brookfield and a Canadian pension fund have expressed interest in the government's stake, per people familiar with the matter; all declined to comment1