2 Sources
[1]
Microsoft-backed AI data center faces backlash over 62 unpermitted gas turbines and 1.5M-gallon LNG tank -- issues with $19.4B facility range from illegal construction to noise pollution
The DataOne data center in Vineland, New Jersey, has faced a slew of complaints from the community since construction began in 2025. According to Stand.earth, the project has reportedly been operating several unpermitted gas turbines on site, spewing air pollution in the area near two local schools. Aside from that, the site has also faced allegations of constructing an unpermitted 1.5-million-gallon liquefied natural gas storage tank and of unacceptable noise levels at night, which affected residents within a half-mile radius of the data center. Matt Williams, chairperson of the Sustain South Jersey group, told Tom's Hardware that construction had already begun even before Nebius signed a multi-year agreement to "deliver dedicated capacity to Microsoft from its new data center in Vineland, New Jersey," in October 2025. However, the residents only became aware that the project was a data center after the $19.4 billion deal to secure around 100,000 Nvidia GB300 GPUs for the tech giant was made public. Vineland residents began seeing references to the data center in various government documents, prompting several questions to the city government. Because of this, the city called a town hall meeting last January 2026 -- several months after construction on the data center had already begun, with DataOne CEO Charles-Antoine Beyney admitting that the meeting should have been initiated several months before. A few weeks before the town hall, some people living within a half-mile radius of the site started complaining about noise from the development. While they couldn't confirm the source of the noise, it was often described as a low hum, similar to that of a generator. A later investigation revealed that the site had 62 gas turbines deployed in the area, with at least 45 running at any given time. This is similar to what SpaceXAI has done in Memphis, Tennessee, where it deployed 69 unpermitted natural gas turbines to power its data centers. While the company has since promised to remove these polluting generators, it will do so only over a span of one year, as they're being slowly replaced by a 1.2-GW on-site power plant. There have also been concerns that the site's stormwater management system does not comply with the state's regulations. A third-party engineering review stated that if these issues are not fixed, they could result in on-site and off-site flooding, especially given the site's massive 55-acre size. The experts also noted that the data center has "underestimated the annual groundwater recharge by at least 20 million gallons per year," which could result in lower aquifer levels and reduce the amount of water available or the water quality for the people living in the area. "The incident should shatter the illusion that Microsoft is a 'good neighbor' or in any way more responsible than the other Big Tech companies," Stand.earth Senior Campaigner Nathan Taft said in the statement. "This investigation has revealed that far from 'doing this work differently than other' as it promised, Microsoft is drawing directly from Elon Musk's xAI playbook of doing the damage first and asking for permission later." In an interview with Tom's Hardware, Nathan said that even though Microsoft does not directly own or operate the Vineland data center, it stands to reason that the tech giant should do something about all these complaints, as it's the one that has contracted Nebius for the computing power, which resulted in DataOne's construction project. He compared this to a contractor making a mess on their client's neighbor's property. Even though a third-party provider -- DataOne -- was at fault for the issue, the fact that the people have already been complaining should give Nebius pause and compel Microsoft to do something. DataOne's actions in New Jersey directly contradict the promise Microsoft made back in January 2026, and residents are asking the tech giant to stand by its word. Although the concerns about air and noise pollution are technically not mentioned in the company's "community-friendly" commitments, these issues still impact the quality of life of the people living around the DataOne data center. Aside from that, the unpermitted construction shows it does not adhere to the rules of Vineland. "The developers have been 'act first, pay the fine, and ask for forgiveness later,'" says Mr. Williams. Follow Tom's Hardware on Google News, or add us as a preferred source, to get our latest news, analysis, & reviews in your feeds.
[2]
Microsoft-backed AI data center has been accused of violating federal law - Engadget
It's allegedly been running dozens of gigantic generators without a permit. The largest planned AI data center in New Jersey has been accused of violating federal law after an investigation found the site running dozens of gas-powered generators without a permit, according to Floodlight and The Guardian. Thermal drone footage showed the partly-finished DataOne facility was operating at least 45 of the site's 62 generators simultaneously. The facility allegedly doesn't have permits for any of them. DataOne is located around 40 miles outside of Philadelphia in Vineland, New Jersey. It provides AI computing power to Microsoft as part of a $17 billion deal with Dutch AI infrastructure giant Nebius. This data center has been controversial since breaking ground in 2025. There have been persistent noise complaints, contentious zoning debates and major blowback from residents. It's located just a mile from two schools. In the age of AI, it's worth discussing the size of all of this stuff. The DataOne site will eventually become a 2.6 million-square-foot behemoth. A standard data center, of the type that powers cloud services, typically comes in at around 100,000 square feet. That's an exponential size difference. The generators are also absolutely massive. Each one is the size of a tractor-trailer or semi-truck. These gigantic machines are gas-powered and emit boatloads of air pollution that have been linked to health conditions like asthma and heart attacks. They are also really, really loud. The noise complaints have led to a lawsuit by residents, which is ongoing. So any site using this type of generator requires "a final permit before bringing" them online "and certainly before firing them up," according to former EPA chief Bruce Buckheit. The thermal drone footage suggests that many are operational, all without permits. Buckheit believes that DataOne's actions "violate federal law" and that the company should immediately cease operations and pay a fine for "their illegal emissions." The facility's lack of proper operational permits has been confirmed by a spokesperson with the New Jersey Department of Environmental Protection. They said that the agency "has issued no permits, nor are any permit applications under review for power generators at the DataOne facility in Vineland." However, the spokesperson also said the agency has to make "a full compliance determination." DataOne hasn't responded to pointed questions regarding the unpermitted generators but said it "remains committed to meeting all applicable and environmental and permitting requirements." That thermal drone footage seems to suggest otherwise. Also, the company has been repeatedly dinged by the city of Vineland, which has issued multiple stop work orders. Nebius and Microsoft haven't issued responses to the allegations. "It seems that this industry, in particular, values speed to market more than almost anything else," Buckheit noted. He went on to say that the people behind DataOne "seem to believe that it's better to ask for forgiveness than for permission." That does seem to be the underlying credo behind most modern AI companies.
Share
Copy Link
DataOne's New Jersey facility faces allegations of violating federal law by running dozens of gas-powered generators without permits. The Microsoft-backed AI data center has sparked community backlash over noise pollution, illegal construction, and environmental concerns near two local schools.
The DataOne AI data center in Vineland, New Jersey has become the center of a growing controversy after investigations revealed the facility operating 62 unpermitted gas turbines without required federal permits
1
2
. Thermal drone footage captured at least 45 of these massive generators running simultaneously, each the size of a tractor-trailer, powering the partly-finished facility that serves Microsoft under a $19.4 billion agreement with Dutch AI infrastructure company Nebius1
2
. The New Jersey Department of Environmental Protection confirmed it has issued no permits for power generators at the DataOne facility, nor are any applications currently under review2
.Residents living within a half-mile radius of the site began reporting disturbing noise pollution several weeks before a town hall meeting in January 2026, describing a persistent low hum similar to generator sounds
1
. The illegal construction extended beyond the unpermitted gas turbines to include a 1.5-million-gallon liquefied natural gas storage tank, or LNG tank, built without proper authorization1
. Located just one mile from two local schools, the facility's gas-powered generators emit substantial air pollution linked to health conditions including asthma and heart attacks2
. Matt Williams, chairperson of Sustain South Jersey, revealed that construction had already begun before residents even knew the project was an AI data center, only discovering its purpose after the deal to secure approximately 100,000 Nvidia GB300 GPUs for Microsoft became public1
.Former EPA chief Bruce Buckheit stated that DataOne's actions violate federal law, emphasizing that any site using this type of generator requires "a final permit before bringing them online and certainly before firing them up"
2
. Buckheit believes the company should immediately cease operations and pay fines for their illegal emissions2
. The environmental impact of AI extends beyond air quality concerns. A third-party engineering review identified serious flaws in the site's stormwater management system, warning that unresolved issues could trigger on-site and off-site flooding across the massive 55-acre property1
. Experts noted the data center has "underestimated the annual groundwater recharge by at least 20 million gallons per year," potentially lowering aquifer levels and compromising water availability and quality for local residents1
.Related Stories

Source: Engadget
The DataOne facility represents an unprecedented scale in AI infrastructure. When complete, the New Jersey data center will span 2.6 million square feet—exponentially larger than standard cloud service data centers that typically occupy around 100,000 square feet
2
. This massive footprint reflects the enormous energy demands of AI computing, particularly for training and running advanced models. The city of Vineland has issued multiple stop work orders against the project, yet construction continues2
. DataOne CEO Charles-Antoine Beyney acknowledged at the January town hall that community engagement should have begun months earlier, before construction started1
. The situation mirrors xAI's controversial deployment of 69 unpermitted natural gas turbines in Memphis, Tennessee, which the company promised to remove over one year as they transition to a 1.2-GW on-site power plant1
.Stand.earth Senior Campaigner Nathan Taft stated, "The incident should shatter the illusion that Microsoft is a 'good neighbor' or in any way more responsible than other Big Tech companies. This investigation has revealed that far from 'doing this work differently than other' as it promised, Microsoft is drawing directly from Elon Musk's xAI playbook of doing the damage first and asking for permission later"
1
. While Microsoft doesn't directly own or operate the Vineland facility, critics argue the tech giant bears responsibility as the primary customer driving the project's existence through its contract with Nebius1
. DataOne's actions directly contradict Microsoft's January 2026 promise to be community-friendly, with residents demanding the company honor its commitments1
. Williams characterized the developers' approach as "act first, pay the fine, and ask for forgiveness later"1
. Bruce Buckheit observed that "this industry, in particular, values speed to market more than almost anything else," suggesting the underlying credo behind most modern AI companies prioritizes rapid deployment over regulatory compliance2
. DataOne responded to inquiries by stating it "remains committed to meeting all applicable environmental and permitting requirements," though has not addressed specific questions about the unpermitted generators2
. Neither Nebius nor Microsoft has issued responses to the allegations. Ongoing zoning debates and a lawsuit filed by residents over noise complaints remain unresolved as the facility continues expanding2
.Summarized by
Navi
06 Jul 2026•Policy and Regulation

10 Jul 2026•Policy and Regulation

26 Apr 2025•Technology

1
Technology

2
Policy and Regulation

3
Technology
