Nvidia considers debt guarantee for Nscale's troubled West Virginia AI data center project

11 Sources

Share

Nvidia is in talks to guarantee billions in debt financing for Nscale's West Virginia AI data center, which will serve Anthropic under a $45 billion contract. The move comes as the AI infrastructure startup faces construction setbacks, regulatory issues, and mounting investor concerns ahead of its planned $35 billion IPO.

News article

Nvidia Steps In With Unprecedented Financial Backing

Nvidia is negotiating to guarantee billions of dollars in debt financing for Nscale's AI data center in West Virginia, marking an unprecedented level of financial support from the chipmaker

1

5

. Under what's known as a residual value guarantee, Nvidia would step in if Nscale defaulted on construction payments, temporarily take over the facility, and help find a buyer and new tenant

1

. This represents a significant shift from Nvidia's earlier support for AI cloud companies, which mostly covered leases and chip purchases rather than construction costs

1

.

The proposed arrangement would help Nscale secure financing for electricity and construction costs at its Monarch Compute Campus. Nvidia has already extended roughly $170 billion in investments and credit support to neoclouds and large customers, including $1 billion in convertible financing committed to Nscale in September

1

. One investor suggested that Anthropic's involvement likely explains Nvidia's interest in keeping the project on track

1

.

Anthropic's $45 Billion Contract Drives Project Forward

Anthropichas signed a $44.6 billion contract with Nscale for the project's first 460-megawatt building alone, according to Nscale's IPO filing

1

. This Anthropic AI data center deal accounts for more than 40% of Nscale's $103 billion revenue backlog

4

. The companies are also discussing a second deal worth roughly $45 billion for another building at the West Virginia data center

1

4

.

The first building is expected to use Nvidia's next-generation Vera Rubin AI chips

1

. However, Nscale said in its IPO filings that it has not yet secured financing to build or equip the first building for Anthropic, and the AI lab can walk away if that debt financing is not secured by a set deadline

4

5

.

Construction Delays and Regulatory Hurdles Mount

The West Virginia AI data center has encountered significant construction delays and regulatory scrutiny. A week before Nscale publicly filed for its IPO in September, West Virginia regulators issued the AI infrastructure startup with a cease-and-desist order halting further construction across the site for three days after runoff from the project repeatedly flooded neighboring properties

4

. Regulators had already ordered part of the site to stop work in July, and the company has received 10 notices of violation for inadequate stormwater controls

4

5

.

The Monarch Compute Campus, billed as a 2,250-acre site with up to 8GW of power, will power its first 2GW phase with 864 gas-fired engines after its original developer lobbied to change state law

4

5

. Its permitted emissions would rank the site among America's 20 biggest sources of greenhouse gases. Running at full capacity, the engines would be permitted to emit 271 tonnes of formaldehyde annually and 10 million tonnes of greenhouse gases per year

4

.

Microsoft Deals Fall Through as Investor Skepticism Grows

Nscale's challenges extend beyond West Virginia. Microsoft pulled out of a planned Nscale site in England after grid power for it was pushed into the 2030s

1

2

. The US software giant also rejected an option to more than double the size of its existing contract to rent computing power at a data center site in Texas

2

3

. The extra capacity could have been worth tens of billions of dollars to the AI cloud company

3

.

Investor skepticism toward AI infrastructure expansion has intensified. Shares of CoreWeave, Nebius, and IREN had each fallen more than 30% in October

1

. AI cloud companies such as CoreWeave, Nebius and Nscale have effectively been shut out of the bond market in recent weeks

5

. Nscale made a net loss of $1 billion on revenue of $141 million in the first half of 2026

2

4

.

IPO Plans Face Uncertain Future

Nscale is seeking to go public at a valuation of up to $35 billion despite growing concerns about its ability to deliver on ambitious AI data center projects

1

3

. The company had about 25,000 advanced AI chips running in August, a fraction of the nearly 500,000 it plans to deploy

1

.

Nvidia and other possible backers began demanding stricter terms after markets turned, delaying Nscale's revised IPO prospectus

5

. Nscale is now leaning towards a December listing rather than November, and some of its bankers have warned that an IPO is unlikely to reach the $30 billion to $35 billion valuation it had targeted

5

. The AI infrastructure startup counts former Meta executive Sheryl Sandberg and former UK deputy prime minister Sir Nick Clegg as board members

2

.

When asked about Nscale's problems getting its data centers online, Nvidia chief executive Jensen Huang told the company to "work around the clock" and "try less sleep, which is what I do"

5

. Chief executive Josh Payne has tried to reassure staff by telling them demand for computing power remained "insatiable"