2 Sources
[1]
Data centers forecast to use 20% of US power by 2035 -- analysts estimate usage will rocket to 194 gigawatts, 83% more than forecast seven months ago
U.S. data centers are on track to consume about 20% of the nation's electricity by 2035, up from 5.9% today, according to a new BloombergNEF forecast The research firm raised its 2035 demand projection to 194 GW, an 83% increase on the forecast it issued in December, and calculated that even a record pace of grid connections sustained every year for a decade would leave a 19 GW supply shortfall. BNEF's December outlook put 2035 demand at 106 GW, and that figure was itself 36% above the projection the firm published in April 2025, which works out to roughly 78 GW. The 2035 number has increased around 2.5 times in 15 months, with the latest jump reflecting the volume of new AI facilities entering the development pipeline rather than capacity actually under construction. Many other forecasters are moving in the same direction, with the electrical industry nonprofit EPRI more than doubling its 2024 estimate and S&P raising its projection by more than a third between October and April. Nearly half of the projected capacity will serve AI training and inference workloads, and the U.S. is expected to host 64% of the world's AI chips by power demand in 2033. BNEF estimates that data centers will account for around 12% of U.S. electricity consumption in 2030 before reaching 20% five years later, with Virginia and Texas running above the national average. Gartner separately forecast that global data center electricity consumption will grow 26% this year, reaching 565 TWh in 2026. The most data center capacity ever connected to the U.S. grid in a single year is 7.1 GW, according to the report. Holding that pace through 2035 still produces a 19 GW shortfall under BNEF's base case, even after accounting for on-site gas generation. Lloyd Arnold, a BNEF analyst and one of the report's authors, told Bloomberg that of the output from "every coal plant, every gas plant, every solar farm in the U.S.," one unit of energy in five will go to data centers. PJM Interconnection, the 13-state grid operator whose territory includes Northern Virginia's data center corridor, will send 34% of its electricity to data centers by 2035, with ERCOT in Texas at 22%, per reporting from TechCrunch. PJM's independent market monitor has already attributed a 75.5% increase in regional power costs directly to data center demand. Close to half of planned U.S. data center builds this year are projected to be delayed or canceled, with lead times for high-power transformers stretching to as long as five years. BNEF's own December revision was driven primarily by early-stage projects that entered utility queues to secure power before construction began, so a meaningful share of the pipeline behind the 194 GW figure remains speculative. Follow Tom's Hardware on Google News, or add us as a preferred source, to get our latest news, analysis, & reviews in your feeds.
[2]
AI surge to drive US data centers to use one-fifth of power by 2035
Data centers are projected to consume one-fifth of the electricity generated in the U.S. by 2035, a fourfold increase from current levels, according to a new report from BloombergNEF. The report predicts that surging demand for AI compute will propel data center capacity to nearly 200 gigawatts over the next decade, with nearly 50% allocated for training and inference, primarily in the U.S. By 2033, the report estimates that the U.S. will host 64% of AI chips by power demand. BloombergNEF's latest electricity demand estimate for 2035 is 83% higher than its previous prediction made in December. Other organizations, including EPRI and S&P, have also revised their electricity demand forecasts upward, reflecting rapid developments in data center infrastructure across the country. In the coming years, most new data centers are expected to connect to electrical grids already under strain. The PJM Interconnection, which serves Virginia to Illinois, will allocate 34% of its electricity to data centers, while ERCOT, covering much of Texas, will allocate 22% of its generating capacity. PJM has faced challenges with connection requests, pausing new applications for four years, which has created precarious conditions amid rising demand. Although PJM reopened its queue for new generating sources in April, the situation remains critical, leading American Electric Power to threaten to withdraw from the interconnection process. This supply-demand imbalance has contributed to a 76% rise in electricity prices over the past year. Data centers represented 38% of charges in PJM's latest capacity auction, indicating continued interest in connecting to the grid despite congestion issues. If aggressive AI adoption trends persist, worldwide data centers could contribute 1,935 terawatt-hours of new electricity demand by 2033, approaching India's annual usage.
Share
Copy Link
Data centers are projected to consume one-fifth of U.S. electricity by 2035, up from 5.9% today, according to BloombergNEF. The firm raised its forecast to 194 gigawatts—an 83% jump from seven months ago—driven primarily by AI training and inference workloads. Even at record grid connection rates, analysts predict a 19-gigawatt supply shortfall.
U.S. data centers are on track to consume approximately 20% of the nation's electricity by 2035, a dramatic escalation from the current 5.9%, according to a new BloombergNEF report
1
. The research firm has raised its 2035 U.S. data center power consumption projection to 194 gigawatts, representing an 83% increase over the forecast it issued just seven months ago in December1
2
. This rapid revision underscores how quickly AI-driven demand is reshaping electricity demand forecasts across the industry.
Source: Tom's Hardware
The AI surge is the primary catalyst behind this explosive growth trajectory. Nearly half of the projected capacity will serve AI training and inference workloads, with the U.S. expected to host 64% of the world's AI chips by power demand in 2033
1
2
. The scale of this transformation becomes clear when examining the trajectory of BloombergNEF's own projections: the December outlook estimated 2035 demand at 106 GW, which was itself 36% above the firm's April 2025 projection of roughly 78 GW1
. In just 15 months, the 2035 forecast has increased approximately 2.5 times, reflecting the volume of new AI facilities entering development pipelines rather than just capacity under construction.The surge in power consumption creates severe grid strain issues, particularly in states like Virginia and Texas, which are expected to run above the national average
1
. PJM Interconnection, the 13-state grid operator covering Northern Virginia's data center corridor, will send 34% of its electricity to data centers by 2035, while ERCOT in Texas will allocate 22% of its generating capacity1
2
. PJM's independent market monitor has already attributed a 75.5% increase in regional power costs directly to data center demand1
. The interconnection process has become so strained that PJM paused new applications for four years, only reopening its queue for new generating sources in April2
.Related Stories
Even at record grid connection rates, the energy infrastructure faces significant challenges. The most data center capacity ever connected to the U.S. grid in a single year is 7.1 GW
1
. Maintaining that pace through 2035 would still produce a 19 GW supply shortfall under BloombergNEF's base case, even after accounting for on-site gas generation1
. Supply chain constraints further complicate grid expansion efforts, with lead times for high-power transformers stretching to as long as five years1
. Close to half of planned U.S. data center builds this year are projected to be delayed or canceled due to these infrastructure bottlenecks.Lloyd Arnold, a BNEF analyst and one of the report's authors, told Bloomberg that of the output from "every coal plant, every gas plant, every solar farm in the U.S.," one unit of energy in five will go to data centers
1
. Other forecasters are moving in the same direction, with the electrical industry nonprofit EPRI more than doubling its 2024 estimate and S&P raising its projection by more than a third between October and April1
. Gartner separately forecast that global data center electricity consumption will grow 26% this year, reaching 565 TWh in 20261
. If aggressive AI adoption trends persist, worldwide data centers could contribute 1,935 terawatt-hours of new electricity demand by 2033, approaching India's annual usage2
.Summarized by
Navi
[1]
10 Jun 2026•Technology

21 Dec 2024•Technology

15 Aug 2025•Business and Economy

1
Technology

2
Policy and Regulation

3
Science and Research
