Data center construction costs soar 13 percent in 2026
* The demand for large-scale data centers in the U.S. this year grew well beyond the supply of powered land and the labor to build these structures. * The demand was driven by the need for computing power for artificial intelligence. * Costs rose 13% year-over-year to more than twice the global
[2]
U.S. data center construction costs rose 13%, outpacing global rate
Turner & Townsend says AI-ready U.S. data centers cost around 10% more to build than traditional facilities Turner & Townsend said in its latest data center cost index that U.S. construction costs climbed 13% in 2026, over double the worldwide pace and roughly triple the decade average. The
Share
Copy Link
Building a data center in the United States cost 13% more in 2026 than last year, per the annual cost index from Turner & Townsend, a global project management firm
1
2
. The rise is more than double the global pace and roughly three times the ten-year average. For anyone building or backing these facilities, the figure points to a supply squeeze that keeps tightening.
Source: Quartz
Per the report, AI-driven demand for large-scale US data centers has outgrown the available supply of powered land and skilled construction labor
1
2
. Speed makes it worse. Paul Barry, the consultancy's North America data center lead, said the rush itself costs money1
. "More aggressive schedules tie to contractors in particular and subcontractors baking in more risk allowances in their pricing." Overtime, acceleration allowances and higher fees for fast delivery all end up in the bill.The index, per the report, draws on more than 500 live or recently completed projects across 62 markets, plus a survey of about 400 industry experts
1
2
. The bottleneck readings come from the people doing the building. Per the survey, a majority of respondents worldwide, 56%, named power a major obstacle to getting projects built1
2
. Just over half said a utility connection takes one to two years; almost a third, 32%, said longer2
.Labor is tight as well. Only about a quarter of North American respondents said contractor capacity was sufficient, and 81% called skilled labor where they operate moderately or highly constrained
2
.Where a project lands matters too. On a standard 60-megawatt design, power runs $15.01 per watt in Silicon Valley against $10.51 in Dallas
1
2
. Per the index, AI-ready facilities cost about 10% more to build than traditional ones, a premium that comes from denser racks, liquid cooling and faster schedules2
.Independent spending data backs the index up. US private companies were building data centers at an annualized pace of roughly $85 billion in August, per Quartz, up 73% from a year earlier
2
. By that month, companies were putting close to twice as much money into data centers as into offices2
. The scale shows up in single projects: in Saline, Michigan, Related Digital is building a $16 billion data center for Oracle and OpenAI1
.PwC projects global data center capital spending climbing from roughly $800 billion this year to $1.8 trillion annually in 2050
1
. The firm expects the US to take almost half of global AI infrastructure investment by then1
.The report did find some easing of cost inflation this year, but not enough to offset growing demand and construction speed
1
. "I think we've hit a big surge in 2026, especially of new big major projects that have been procured," Barry said1
. He expects increases to moderate to between 6% and 10% next year, if demand holds, since most major projects have already started and their contracts carry the cost risk1
2