Microsoft's massive Kenya AI data center would require switching off 'half the country' to meet power requirements, government says -- $1 billion project stalls over capacity disagreements and lack of infrastructure
A $1 billion data center that Microsoft and Abu Dhabi-based AI firm G42 planned to build in Kenya has stalled after the Kenyan government failed to meet Microsoft's demand for guaranteed annual capacity payments, Bloomberg reported Sunday. Kenyan President William Ruto put the scale of the
[2]
Microsoft's African data center falters on payment demands, Bloomberg News reports
May 10 (Reuters) - A Microsoft (MSFT.O), opens new tab data center site in East Africa has been delayed by disagreements with the Kenyan government over the company's request for guaranteed payments, Bloomberg News reported on Sunday citing people familiar with the matter. In May 2024, Microsoft
[3]
Microsoft-G42 Kenya data centre stalls over government offtake demands
The company asked the Kenyan government for a guaranteed annual capacity offtake. The government did not commit at the level Microsoft requested. Talks have broken down for now; the project is not formally cancelled. A $1bn Microsoft data-centre project in Kenya, structured as a partnership with
[4]
Kenya tells Microsoft that $1 billion AI data center would gulp half the country's electricity
The proposed facility reportedly demands electricity on a scale the country simply cannot afford right now. The AI industry keeps talking about bigger models, faster chips, and trillion-parameter futures. What it talks about far less is the absolutely absurd amount of electricity needed to keep
[5]
'We would need to shut off power for half the country': Microsoft's $1 billion Kenya data center project runs out of juice
'Future generations will be overburdened by the current decisions.' Plans to build potentially the biggest, most expensive data centre in East Africa have stalled. Sources close to the matter say that talks between the Kenyan government and Microsoft have broken down due to disagreements over
[6]
Microsoft's African data center falters on payment demands, Bloomberg News reports - The Economic Times
A Microsoft data center site in East Africa has been delayed by disagreements with the Kenyan government over the company's request for guaranteed payments, Bloomberg News reported on Sunday citing people familiar with the matter. In May 2024, Microsoft partnered with UAE-based AI firm G42 to
[7]
Microsoft's African data center falters on payment demands, Bloomberg News reports
May 10 (Reuters) - A Microsoft data center site in East Africa has been delayed by disagreements with the Kenyan government over the company's request for guaranteed payments, Bloomberg News reported on Sunday citing people familiar with the matter. In 2024, Microsoft partnered with UAE-based AI
Share
Copy Link
Microsoft and G42's ambitious $1 billion AI data center project in Kenya has hit a major roadblock over power capacity disputes. President William Ruto says the facility would require shutting off half the country's electricity to operate, highlighting the massive energy demands of AI infrastructure in developing economies.
A $1 billion Microsoft Kenya data center project has stalled after the Kenyan government failed to meet the tech giant's demands for guaranteed annual capacity payments, according to Bloomberg reports
1
2
. The facility, planned as a partnership between Microsoft and Abu Dhabi-based AI firm G42, was announced in May 2024 during President William Ruto's state visit to Washington. The geothermal-powered data center was set to bring Microsoft Azure services to the East African region through a new cloud computing services hub in the Olkaria area of Kenya's Rift Valley1
. Microsoft and G42 requested that Kenya commit to purchasing a defined amount of computing capacity annually, but negotiations broke down when the government couldn't provide the offtake guarantee at the level Microsoft requested3
.
Source: PC Gamer
The scale of the AI data center's power requirements has become the central obstacle. President William Ruto articulated the challenge bluntly at a recent state event in Nairobi, saying the country would need to "switch off half the country" to keep the facility running
1
5
. Kenya's total installed electricity capacity sits between 3,000 and 3,200 megawatts, with peak demand reaching a record 2,444 megawatts in January, according to KenGen data1
. The first phase of the project targeted 100 megawatts of capacity with a long-term goal of scaling to 1 gigawatt1
. That full build would consume roughly a third of Kenya's total capacity, while even the initial 100 megawatts would require a significant share of the Olkaria geothermal complex's output, which currently generates around 950MW1
.The offtake demand represents an unusual approach for hyperscaler investment in data center expansion. Microsoft applied this commercial structure because the local enterprise market alone isn't large enough to justify a $1 billion facility, and financing partners increasingly insist on guaranteed revenue floors for projects in higher-risk geographies
3
. However, Kenya's government, facing a tight fiscal environment and IMF programme conditions, couldn't commit to multi-year capacity payments when health, education, and power infrastructure spending are under pressure3
. John Tanui, principal secretary at Kenya's Ministry of Information, told Bloomberg that the project hasn't been withdrawn and talks continue, noting that "the scale of the data center they wanted to do still requires some structuring"1
2
.Related Stories

Source: Reuters
The Kenya facility was set to be the first that Microsoft and G42 built together after Microsoft invested $1.5 billion in G42 in 2024
1
5
. That deal followed G42's agreement to divest from Chinese holdings and strip Huawei equipment from its systems under pressure from Washington. Microsoft President Brad Smith joined G42's board as part of the arrangement and described the Kenya project as the "single biggest step forward" for digital technology and AI in the country's history1
5
. The stall carries reputational costs for Kenya, as the facility was meant to anchor an East African digital hub spanning Rwanda, Uganda, Tanzania, and Ethiopia, with downstream effects on submarine cable landings, fintech build-out, and AI talent pipelines3
.The Kenya situation reflects broader challenges facing AI infrastructure globally. Microsoft is spending $190 billion on capex in 2026 and adds approximately 1 gigawatt of data center capacity every three months globally
1
5
. However, power constraints are proving to be a universal bottleneck, with nearly half of planned U.S. data center builds this year delayed or canceled due to shortages of electrical infrastructure1
. The uncomfortable reality is that AI's massive energy demands are becoming harder to ignore, with data centers already consuming significant shares of electricity in major markets4
. Microsoft separately announced a $329 million expansion in South Africa last month, partly framed as a hedge against East African delays, ensuring Azure Africa footprint continues growing even if Kenya doesn't deliver on the original timeline3
. President Ruto is making the case to expand Kenya's energy infrastructure capacity to 10,000 megawatts by 2030, leveraging the Olkaria data center as one driving example, though Auditor General Nancy Gathungu expressed concerns, warning that "future generations will be overburdened by the current decisions"5
. Whether Microsoft and G42 return to the table depends on whether Nairobi can offer a structure that gives operators revenue certainty without breaching fiscal constraints, with a scaled-back facility or different financing partner remaining possibilities3
.Summarized by
Navi