President Lee Jae Myung toured the construction site of a large AI data center in Ulsan on Saturday. It came a day after he wrapped up a four-day trip that took in the Philippines and China

3

. The visit signals presidential-level attention to a project the government counts among its priorities

1

.

Source: Korea Times

Source: Korea Times

A project built for the race

The center Lee toured is a joint project of SK Group, South Korea's second-largest conglomerate, and Amazon Web Services

1

. The science ministry estimated last year it would cost 7 trillion won, about $5.2 billion, through 2029, with operations set to begin in the second half of 2027

1

. SK Chairman Chey Tae-won said in September the initial capacity under construction is 103 megawatts by 2029, with plans to expand by nearly 900 megawatts later

2

.

Why the urgency? "The whole world is competing right now, and speed is vital," Lee said at the site

1

. He argued the centers matter twice over: they are a major source of semiconductor demand, and they are key infrastructure for physical AI, from robots to autonomous vehicles

3

.

Workers and regions

About 900 workers were reported on site during the visit

1

. Lee said advanced facilities like this one lack construction workers, and he asked ministries to consider training workers for data centers and AI infrastructure

2

.

He said he came to check progress on the government's mega projects, part of a program to build regional industry hubs outside Seoul

3

. Lee said AI investment has mainly been concentrated around Seoul, and a project like Ulsan shows growth elsewhere is possible

1

.

"I expect the successful progress of the AI data center project in Ulsan will serve as a catalyst for additional investments from global AI companies," Lee said

3

.